Smart EPD
Fabrication Process for Structural Steel

Environmental Product Declaration

Fabrication Process for Structural Steel

by American Institute of Steel Construction

Environmental Product Declaration (EPD) for Fabrication Process for Structural Steel, manufactured by American Institute of Steel Construction. Declaration SmartEPD-2025-092-0615-01.2, prepared according to Smart EPD® Part B PCR for Designated Steel Construction Products, 1000-008, v3.0, valid until October 15, 2030.

Download the EPD (PDF)

Declared unit
1 unit of fabrication required for 1 MT of fabricated structural steel of product
Valid until
October 15, 2030
PCR
Part B PCR for Steel Construction Products

Declaration details

Manufacturer
American Institute of Steel Construction
Program operator
Smart EPD
Declaration number
SmartEPD-2025-092-0615-01.2
Date of issue
October 15, 2025
Valid until
October 15, 2030
Product category rules (PCR)
Smart EPD® Part B PCR for Designated Steel Construction Products, 1000-008, v3.0 (version 3)
Standard
ISO 14025:2006 and ISO 21930:2017
Declared unit
1 unit of fabrication required for 1 MT of fabricated structural steel of product
System boundary
Cradle to gate (A1 - A3)
Product specificity
Product Average
Manufacturing specificity
Industry Average
Product category
Steel › StructuralSteel
Verifier
Rifat Karim, Independent Consultant
LCA software
openLCA 2.4
Program instructions
Smart EPD General Program Instructions v.2.0, March 2025

Life cycle assessment results

Results per 1 unit of fabrication required for 1 MT of fabricated structural steel of product.

Environmental Impact Assessment Results

IndicatorUnitA1A2A3
GWP-totalkg CO2 eq7.71%2.62e+18.24e+1
GWP-fossilkg CO2 eq7.71%2.62e+18.23e+1
GWP-biogenickg CO2 eq7.71%1.85e-34.27e-2
GWP-luluckg CO2 eq7.71%1.71e-35.48e-2
ODPkg CFC 11 eq7.71%5.41e-77.72e-7
APkg SO2 eq7.71%9.89e-22.15e-1
EPkg N eq7.71%1.13e-11.08e-1
POCPkg O3 eq7.71%2.77e+02.70e+0
ADP-fossilMJ7.71%5.06e+21.13e+3

Resource Use Indicators

IndicatorUnitA1A2A3
RPREMJ7.71%1.11e+01.50e+2
RPRMMJ7.71%00
NRPREMJ7.71%5.03e+21.46e+3
NRPRMMJ7.71%00
SMkg7.71%00
RSFMJ7.71%00
NRSFMJ7.71%00
FWm37.71%5.51e-33.72e-1
REMJ7.71%00

Waste and Output Flow Indicators

IndicatorUnitA1A2A3
HWDkg7.71%3.53e-34.08e-3
NHWDkg7.71%7.05e-21.23e+1
RWDkg000
HLRWkgN/AN/AN/A
ILLRWkgN/AN/AN/A
CRUkg000
MFRkg7.71%07.71e+1
MERkg7.71%00
EEEMJ7.71%00

ND = not declared. Life cycle modules: A1-A3 product stage, A4-A5 construction process, B use stage, C end of life, D benefits and loads beyond the system boundary.

Material composition

Product composition
Material/Component CategoryOrigin% Mass
N/AN/AN/A
Packaging
Packaging materialOriginMass (kg)

Hazardous substances

No regulated hazardous or dangerous substances are included in this product.

Product description

Important Note: This EPD represents the fabrication process for 1 MT of structural steel. It is intended to be additive to structural steel product EPDs and to serve as a data source for the modeling of the fabrication process in structural steel product EPDs and whole building LCA tools.

Prior to installation, structural steel commonly undergoes a scenario-specific fabrication process. This process entails inspection, material handling, cutting, drilling, fit-up, welding, and bolting; all according to the AISC Code of Standard Practice for Steel Buildings and Bridges (ANSI/AISC 303-22). In addition to the steel itself, inputs to fabrication include relatively small amounts of process materials, such as lubricants, gases, electrodes, and welding fluxes. Some facilities also conduct surface preparation using mechanical processes or compressed air blasting in order to clean the surface and prepare it for coating. Surface preparation for the application of coatings, the coatings themselves, and galvanization are not included in the scope of this study. Scrap generated during the fabrication processes is considered manufacturing scrap and is returned to steel mills as a pre-consumer external scrap input.

Interpretation

The contribution analysis for the fabrication stage (A3), based on a gate-to-gate assessment of the fabrication process, found that electricity consumption is the largest contributor across all impact categories, representing between 52 and 75 percent of the total. Welding gases are also significant contributors to all impacts (up to 28%) and other energy consumed at the sites is significant for ODP and ADPf.

For the fabrication process needed for 1 metric ton of fabricated structural steel, the average, 10th percentile, and 90th percentile GWP values were calculated from the 80 fabrication facilities that provided primary data for modules A2 (transportation to fabrication) and A3 (fabrication). For A2, the 10th percentile, average, and 90th percentile GWP results were 26, 26, and 28, kg CO2eq/MT, respectively. For A3, the 10th percentile, average, and 90th percentile impacts were 29, 82, and 256 kg CO2eq/MT, respectively.

Figure 2. Contribution analysis results for the U.S. average fabrication process

LCIA results are relative expressions and do not predict impacts on category endpoints, the exceeding of thresholds, safety margins or risks. EPDs are comparable only when they follow the same PCR, functional unit and system boundary. The full EPD (PDF) contains the methodology, scenario assumptions and verification statement.